NSE-listed manufacturers of power transformers, switchgear, and transmission & distribution equipment riding a multi-year capex super-cycle driven by grid expansion, renewable integration, and rising electricity demand.
Sectors represented: Capital Goods, Construction
Expanded capacity in the Distribution Transformers (T2) business. from 5,000 MVA to 9,900 MVA apacity Expansion. Increased capacity in the Power Transformers (T3) business from. 40,000 MVA to 65,000 MVA. Expanded capacity in the Distribution Transformers (T2) business. from 5,000 MVA to 9,900 MVA. Overall transformer manufacturing capacity increased from. 42,400 MVA to 74,900 MVA during the year.
Continuous investments in infrastructure, advanced. manufacturing technologies and testing capabilities. have strengthened our execution capacity, enhanced. operational efficiency and enabled us to address. evolving customer requirements across domestic and. international markets. and testing capabilities. have strengthened our execution capacity, enhanced.
Policies aim to support renewable integration, peak management, and grid stability. . Strong push expected to attract large private investment and domestic manufacturing. Investor Presentation. 8. 34.07%. CAGR. 17.56%. CAGR port renewable integration, peak management, and grid stability. . Strong push expected to attract large private investment and domestic manufacturing. Investor Presentation. 8...
Our plant configuration allows us to produce the CRGO Lamination and CRGO Core based on. the different requirements of our customers pertaining to the dimensions, size and material. requirements. Both our manufacturing facilities are equipped with the latest machineries. different requirements of our customers pertaining to the dimensions, size and material. requirements.
Design of 220kV-140MVA transformer with dynamic short circuit. capability for Data Centers. 2024-25No. In process, multi-. year development. Rolling stock Traction Transformers for Vande Bharat train and metro. applications. 2024-25Yes. HV Switchgear: mic short circuit. capability for Data Centers. 2024-25No. In process, multi-. year development.
We are now. equipped to build for the grid India. is constructing, rather than the one. it has. Our installed capacity gives an idea. of our capability, but it provides an. incomplete picture, as it says nothing. about the size of machine our. manufacturing units can physically. handle. one. it has. Our installed capacity gives an idea. of our capability, but it provides an.
Conducted per standards like IEC. 60076-5, it ensures components do not. deform or fail under maximum peak. currents. FY23FY24FY25FY26H1FY27. Product-wise Order Book (₹. sses. generated by a sudden fault. Conducted per standards like IEC. 60076-5, it ensures components do not. deform or fail under maximum peak. currents. FY23FY24FY25FY26H1FY27. Product-wise Order Book (₹. Cr). 3.
TRANSFORMERS MANUFACTURING BUSINESS OVERVIEW. POWER TRANSMISSIONRAILWAYSRENEWABLESDISTRIBUTION. #. Scott transformers introduced in FY25 portfolio. POWER TRANSFORMERS. High-voltage grid stepping for. long-distance power. transmission with low energy. loss R TRANSMISSIONRAILWAYSRENEWABLESDISTRIBUTION. #. Scott transformers introduced in FY25 portfolio. POWER TRANSFORMERS.
Gas Insulated Switchgears up to 420 kV. »Indoor Switchgears. ◊Up to 12 kV, 50 kA, 4000 A for thermal, nuclear,. hydro and combined cycle power plant projects. ◊Up to 36 kV, 31.5 kA, 2500 A for industries, solar ulated Switchgears up to 420 kV. »Indoor Switchgears. ◊Up to 12 kV, 50 kA, 4000 A for thermal, nuclear,. hydro and combined cycle power plant projects.
Rs.100 Crore, the facility substantially expands our production. capabilities while enabling entry into the high-capacity, high-voltage. transformer segment. With the ability to manufacture transformers up to 200 MVA and 220 kV,. the new facility broadens our addressable market beyond conventional nto the high-capacity, high-voltage. transformer segment.
Tie up with L&T – access to over 350 dealers in India; own. network for modular switches with 50 stockists in 4. southern & western states. Direct network across 50 countries with 40 international. distributors. WIDE DISTRIBUTION NETWORK. Strong engineering capabilities backed by in-house hes with 50 stockists in 4. southern & western states.
Lead times for large power. transformers have extended to three. to four years in several markets, driven. by grid modernisation, renewable. interconnections, data centre load. growth and replacement of ageing. fleets. r large power. transformers have extended to three. to four years in several markets, driven. by grid modernisation, renewable. interconnections, data centre load.
The electrical power equipment sector is undergoing a pivotal transformation as utilities worldwide accelerate efforts to. modernize and digitize ageing grid infrastructure. wer Equipment. Introduction. The electrical power equipment sector is undergoing a pivotal transformation as utilities worldwide accelerate efforts to. modernize and digitize ageing grid infrastructure.